In a significant step towards strengthening power infrastructure in South Andaman, the Electricity Department has successfully augmented an additional 10 MW of generation capacity at the Chatham Power House, with the continued support of the UT Administration.

According to officials, the newly installed 10 MW power unit was successfully tested at full capacity on April 14 in the presence of departmental engineers. The unit is now expected to be commissioned for commercial operations within the next three to four days.

Once operational, the enhanced capacity is expected to provide much-needed relief to residents of Sri Vijaya Puram and adjoining areas, which have been experiencing power constraints in recent days.

The current strain on power supply has been attributed to the sudden breakdown of five diesel generator (DG) sets, temporarily affecting the overall generation capacity in South Andaman. Officials, however, stated that efforts are underway on a war footing to restore these DG sets, with full functionality expected to be achieved within a week.

Meanwhile, the Electricity Department has appealed to consumers to use electricity judiciously during this interim period. Responsible consumption, officials noted, will help bridge the supply gap until all generating units are restored and the new capacity becomes fully operational.