Sri Vijaya Puram | September 10, 2026
The long-envisaged 50 MW Liquefied Natural Gas (LNG)-based power project at Hope Town in Sri Vijaya Puram has entered the implementation phase, marking a significant step forward for the proposed power generation facility in South Andaman.
According to the Electricity Department, Andaman & Nicobar Administration, the development follows the signing of the Power Purchase Agreement (PPA) between NTPC Limited and the Andaman & Nicobar Administration on July 21, 2026.
Subsequently, NTPC Vidyut Vyapar Nigam Limited (NVVN), the project implementation agency, issued the Letter of Award (LoA) on August 28, 2026, for both the Engineering, Procurement & Construction (EPC) Package and the Civil Package. The awards have paved the way for commencement of execution of the project.
The project is scheduled to be commissioned within 28 months from the date of award of the EPC Package.
Once operational, the LNG-based power plant is expected to improve the reliability and efficiency of power supply in South Andaman while reducing dependence on diesel-based generation. The shift towards LNG-based generation is also expected to lower the cost of power generation and contribute to long-term energy security for the islands.
The Electricity Department expressed gratitude to the Ministry of Home Affairs, Ministry of Power, NVVN, Indian Oil Corporation Limited (IOCL) and other stakeholders for their continued guidance, support and coordinated efforts in advancing the project from the planning stage to implementation.
The Department stated that it would continue to extend all necessary support to facilitate the timely completion and commissioning of the project.