Middle Andaman Power Crisis: One Affected DG Back Online After Authorised Service Provider’s Engineer Reaches Rangat Power House

Tarun Karthick
6 Min Read

Sri Vijaya Puram | September 29, 2026

The power situation in Rangat and adjoining areas has shown signs of improvement, with an engineer who travelled from Bengaluru reaching Rangat and taking up work on the defective controllers at the Rangat Bay Power House. As of the latest information received on September 28, one of the affected Diesel Generator (DG) sets had been brought back online after its controller was programmed and commissioned, while work was continuing to restore the other DG set.

As per Circular No. 219 dated September 27, 2026, issued by the Office of the Executive Engineer (Rural), Electricity Department, Rangat Bay, DG-1 and DG-2 at the Rangat Bay Power House had lost communication with the other DG sets, making synchronisation and load sharing impossible.

The circular stated that the controllers of both affected DG sets were found defective, while the available spare controller was also experiencing technical issues. This had resulted in a generation deficit of approximately 1.6 MW. Four controllers were being sent from Swaraj Dweep, while assistance from the authorised service provider had been sought for programming and commissioning of the controllers, with service personnel expected to be deputed for the work.

Speaking to Nicobar Times, Mr. R. Madhavan, former Up-Adhyaksh of Zilla Parishad, North and Middle Andaman District, and Zilla Parishad Member from Nimbutala Constituency, which is among the affected areas, said that an engineer who travelled from Bengaluru to Sri Vijaya Puram on September 28 reached Rangat in a special convoy along with the concerned Executive Engineer.

Mr. Madhavan said the engineer started working at the Rangat Power House and successfully programmed and commissioned one of the controllers, following which one of the affected DG sets was brought online and started supplying power.

He said that, at least for the time being, the duration of power disruption appeared to have reduced to around 1.5 hours, compared to the longer interruptions experienced earlier. However, Mr. Madhavan could not confirm whether the load-shedding schedule issued by the Electricity Department would be revised or whether the duration of the power cuts would be reduced.

He further informed that work was continuing to bring the other affected DG set online.

The September 27 circular had stated that rotational load shedding would be followed and repeated until restoration of the DG sets. For Rangat, the notified load-shedding periods were 12 midnight to 3 am, 4:30 am to 7:30 am, 9 am to 12 noon, 1 pm to 3 pm, 4 pm to 6 pm and 7:30 pm to 10:30 pm. For Nimbutera, the schedule was 3 am to 6 am, 7:30 am to 10:30 am, 12 noon to 2 pm, 3 pm to 5 pm, 6 pm to 9 pm and 10:30 pm to 1:30 am the following day. For Baratang, the notified periods were 1:30 am to 4:30 am, 6 am to 9 am, 10:30 am to 1 pm, 2 pm to 4 pm, 5 pm to 7:30 pm and 9 pm to midnight.

The Electricity Department, in the circular, had expressed regret over the inconvenience caused to the general public and electricity consumers and requested all concerned to bear with the Department during the period.

Mr. Madhavan also informed Nicobar Times that issues at the Kadamtala and Baratang power generation facilities were putting additional load on the Rangat Power House. He said that the Kadamtala Power Generation Facility was also undergoing repairs and was expected to start functioning from September 29.

Meanwhile, a 48-hour ultimatum has reportedly been given to the department by PRI members and members of the general public of the region, beginning from the morning of September 29, demanding an end to the power crisis being faced by the region.

Mr. Madhavan also demanded that the process for replacement of the existing Diesel Generators be initiated at the earliest. According to him, the DG sets at the Rangat Power House are very old, and continued reliance on the ageing generators could lead to further technical problems in the future. He said that unless the replacement of the old DG sets is planned and initiated soon, serious disruptions may arise again.

With the ongoing repair and commissioning work, the power situation in Rangat and surrounding areas may improve by the end of September 29, with consumers expected to receive power in a more normal manner if the remaining restoration work progresses successfully.