Middle Strait Creek Bridge Set to Miss Yet Another Deadline; Question Is, How Many More?

6 Min Read

Sri Vijaya Puram | September 29, 2026

The long-delayed Middle Strait Creek Bridge, a key link between South Andaman and North and Middle Andaman, appears set to miss yet another completion deadline, with the project recording only 13% cumulative physical progress and 11% cumulative financial progress, according to the latest project status published by the National Highways & Infrastructure Development Corporation Limited (NHIDCL) on its website.

The project involves the construction of a 1.96-km major bridge over Middle Strait Creek between Km 106.590 and Km 108.553 of NH-04 (earlier NH-223), connecting South Andaman with Baratang Island. The balance work is being executed under an EPC contract at a total project cost of ₹371.88 crore. The current contractor is RKEC Projects Ltd.-YFC Projects Pvt. Ltd. (JV). The contract was awarded on March 16, 2024, while the appointed date was May 7, 2024.

The original completion date under the new contract was February 25, 2026. However, NHIDCL’s current project status lists December 31, 2026 as the likely date of completion. With only around three months remaining until this revised target and the physical progress standing at just 13%, the project is once again facing a substantial delay.

The present contract is, in fact, a balance work contract, after the contractor appointed under the earlier contract failed to complete the bridge. M/s Mantena Constructions Pvt. Ltd.-Vasishta Constructions Pvt. Ltd. Bridge (JV) had originally been awarded the work. NHIDCL’s project records show that the earlier contract had an original completion date of January 2, 2022, and the contract was subsequently terminated in July 2023.

Following the termination of the earlier contract, the remaining works had to be taken up afresh through a new tender. NHIDCL subsequently awarded the balance work to RKEC Projects Ltd.-YFC Projects Pvt. Ltd. (JV) in March 2024, with the appointed date in May 2024.

The repeated delays have prolonged the difficulties faced by residents and other road users travelling between South Andaman and North & Middle Andaman. The Middle Strait Creek Bridge remains a crucial missing link in the NH-04 corridor, even as the bridge over Humphrey Strait connecting Baratang and Middle Andaman has already been completed and is operational as the Azad Hind Fauj Setu (1,020 metres).

The Middle Strait Creek Bridge is particularly significant for achieving a more continuous and reliable road connection along the Andaman Trunk Road. At present, vehicles have to cross the Middle Strait Creek by vehicle ferries, which adds to travel time as vehicles have to wait for their turn to use the ferry. Commercial vehicles are among the most affected, as private and passenger vehicles are given priority.

The situation is further complicated by the fact that the road leading to Middle Strait from Jirgatang passes through the Jarawa Reserve, where vehicles have to travel in regulated convoys at fixed timings. As a result, vehicles travelling from the Sri Vijaya Puram side often reach Middle Strait together, leading to delays in crossing the creek by ferry to Baratang for onward travel. Similarly, vehicles crossing from Baratang to Middle Strait have to reach in time to make it for the scheduled convoys towards Jirgatang, as the convoy timings are fixed. This makes the journey particularly difficult and time-consuming, especially for commercial vehicle operators and, at times, even for private vehicles when ferry services are reduced due to circumstances such as maintenance requirements.

The prolonged construction of the bridge has meant that the benefits expected from the NH-04 connectivity improvements have remained incomplete for years. The situation is compounded by the condition of the NH-04 road stretch between Kadamtala and Diglipur, where road improvement and construction works have also faced considerable delays under NHIDCL. With both the Middle Strait Creek Bridge and important stretches of the highway yet to be completed or improved as expected, the overall connectivity benefits of the NH-04 project continue to remain out of reach for residents of North and Middle Andaman.

The latest NHIDCL figures indicate that the December 31, 2026 target is unlikely to be achieved, given the low level of progress recorded so far. Even with a substantial increase in the pace of execution, the bridge is likely to move beyond its stated completion date, leaving residents to ask a familiar question: how many more deadlines will the Middle Strait Creek Bridge miss before it is finally completed?