MP Reviews Progress of NH-4 Works; NHIDCL Assures Completion Within Agreed Timelines

Tarun Karthick
3 Min Read

Sri Vijaya Puram | August 20, 2026

Andaman & Nicobar Islands MP Mr. Bishnu Pada Ray reviewed the progress of ongoing National Highway-4 (NH-4) upgradation and reconstruction works with officials of the National Highways & Infrastructure Development Corporation Limited (NHIDCL) at the NHIDCL Regional Office in Prothrapur.

The review meeting followed a field inspection of various stretches of NH-4 in North and Middle Andaman by an NHIDCL team headed by the Director, NHIDCL, Delhi. The visit was undertaken on the direction of the Managing Director, NHIDCL, following the MP’s meeting with the NHIDCL Managing Director in New Delhi on July 29, 2026.

During the meeting, the status of individual NH-4 stretches and packages was reviewed in detail in the presence of NHIDCL officials and concerned contractors. The reasons for delays were discussed, with specific completion timelines fixed for the respective stretches in accordance with the contractual agreements.

NHIDCL officials informed the MP that work on some stretches had been delayed due to negligence and poor performance by certain contractors. This had resulted in termination and re-awarding of contracts, causing further delays. Fresh contracts have since been executed, and efforts are underway to complete the works within the timelines stipulated in the new agreements.

The bridge connecting Middle Strait and Baratang was also discussed. NHIDCL officials informed that similar contractual issues had affected the project and that necessary steps were now being taken to execute and complete the work within the timeline prescribed under the new contract.

Mr. Bishnu Pada Ray emphasized that the prolonged delay in NH-4 works has caused considerable hardship to residents of North and Middle Andaman. Commuters, transport operators, travel agents and other road users have been facing difficulties due to the deteriorated condition of the highway.

Highlighting NH-4’s importance as the main road link connecting the Islands, the MP stressed that the ongoing works should be accorded priority and completed without further delay. He also called for strict monitoring and supervision of the projects and fixing responsibility wherever lapses are found.

NHIDCL officials assured the MP that strengthened supervision by engineers and closer monitoring of contractors would be undertaken to ensure completion of the ongoing works within the target dates stipulated in the respective agreements. They also assured that necessary measures would be taken to improve road conditions and minimize inconvenience to the public during execution of the works.