Power Purchase, Land Use Right and Gas Supply Agreements Signed for 50 MW LNG-Based Power Project at Hope Town

Tarun Karthick
3 Min Read

Sri Vijaya Puram | July 22, 2026

The Andaman & Nicobar Administration on Tuesday signed key agreements for the implementation of the proposed 50 MW LNG-Based Power Project at Hope Town, Sri Vijaya Puram, marking a major step towards strengthening the Islands’ long-term energy infrastructure.

The Power Purchase Agreement (PPA) and Land Use Right Agreement (LURA) were signed between the Electricity Department, A&N Administration and NTPC Vidyut Vyapar Nigam Limited (NVVN), while the Gas Supply Agreement (GSA) was signed between NTPC and Indian Oil Corporation Limited (IOCL). The agreements were signed in the presence of the Chief Secretary, A&N Administration, at the Secretariat.

The signing follows the approval accorded by the Ministry of Power, Government of India, on June 16, 2026, for the Power Purchase Agreement and Gas Supply Agreement for the establishment of the 50 MW LNG-Based Power Project, including a Floating Storage Regasification Unit (FSRU), at Hope Town.

The ceremony was attended by Ms. Renu Narang, Chief Executive Officer of NTPC Vidyut Vyapar Nigam Limited (NVVN), Mr. Prasun Kumar Mishra, Country Head (Gas Business), Indian Oil Corporation Limited (IOCL), along with senior officials of the A&N Administration, IOCL, NVVN and NTPC.

The project will be developed as a Floating Storage and Regasification Unit (FSRU)-based Liquefied Natural Gas (LNG) power plant at Hope Town. The Andaman & Nicobar Administration has already allotted 0.82 hectare of land for the project, while IOCL will develop the LNG receiving, storage and regasification infrastructure. The project is targeted for commissioning by August 2028.

According to the Electricity Department, the 50 MW LNG-Based Power Project is one of the most significant power infrastructure initiatives undertaken in recent years to strengthen the long-term energy security of Sri Vijaya Puram. The project is expected to introduce cleaner and more efficient LNG-based power generation, reducing dependence on diesel-based generation while lowering fuel costs, improving operational efficiency and reducing environmental impact.

The project is also expected to enhance grid stability, improve the reliability of power supply, create adequate reserve generation capacity and cater to the growing electricity demand driven by urban expansion, tourism, commercial activities and future developmental projects in Sri Vijaya Puram.

The Electricity Department stated that the approval of the PPA reflects the Government of India’s continued commitment to strengthening infrastructure in the Andaman & Nicobar Islands and supporting the sustainable development of the strategically important Union Territory.

Expressing gratitude to the Ministry of Home Affairs, Ministry of Power, NTPC, NVVN, IOCL and other stakeholders, the Electricity Department said the execution of the PPA, GSA and LURA marks a significant milestone towards the timely implementation of the project and reinforces the Administration’s commitment to providing modern, reliable and sustainable power infrastructure for the people of the Andaman & Nicobar Islands.