NTPC Limited has invited international competitive bids for the Great Nicobar Island Gas Engine Power Project, with a rated capacity of 108 MW ±5 MW, under an Engineering, Procurement and Construction package.

The tender was issued on August 6, 2026. Bids are to be submitted online through NTPC’s GePNIC portal under a single-stage, two-envelope system comprising a techno-commercial bid and a price bid.

The EPC scope covers the design, engineering, supply, erection, testing and commissioning of the engine-based gas power project on a single-point-responsibility basis, including civil works. It includes gas engines and generators, exhaust and continuous-emission-monitoring systems, gas and air-intake systems, cooling systems, control and instrumentation systems, transformers, 132/33 kV indoor GIS, switchgear, cables, fire protection, auxiliary systems, rooftop solar and related facilities.

The engines must be compatible with firing a blend containing 20% to 25% hydrogen by volume along with RLNG. The tender states that the plant is expected to operate for its life on RLNG while retaining this hydrogen-blending capability.

The contractor’s scope also includes transportation of equipment to Great Nicobar, including customs and port clearances where applicable. Any infrastructure required to transport engines and other plant materials to the project location, including a temporary jetty or connecting road, is also placed within the bidder’s scope.

The package further includes reliability, performance-demonstration and owner-acceptance tests, supply of spares, and one year of O&M supervision after successful completion of the initial or trial operations and performance-guarantee tests, including demonstration tests, whichever occurs later. The contractor must also execute civil, structural, architectural and electrical works for an enabling township.

The required bid security is Rs. 20 crore, or USD 2,076,500.

Bids must be submitted by September 8, 2026, up to 1 p.m. IST. The techno-commercial bids are scheduled to be opened at 3:30 p.m. on the same day, while the price-bid opening date will be intimated separately.

Class-I local suppliers, Class-II local suppliers and non-local suppliers are eligible to participate, but purchase preference will be given to Class-I local suppliers.

The qualifying requirements include alternative technical eligibility routes for an engine manufacturer, an EPC contractor associated with a qualifying engine manufacturer, and an Indian subsidiary of a qualifying engine manufacturer. The bidder’s average annual standalone turnover for the preceding three financial years must be at least Rs. 3,469 million, or Rs. 346.9 crore.

The uploaded Invitation for Bids does not state an overall estimated contract value. It says that the detailed scope, specifications and commercial conditions will be governed by the complete bidding documents. NTPC has also reserved the right to reject any or all bids or cancel or withdraw the invitation without assigning a reason.

The 108 MW Gas Engine Power Project is one of the four key pillars of the Great Nicobar Island (GNI) Project, with the other three being the Dual-Use Greenfield International Airport, Township and the Transshipment Port.