Great Nicobar Project: Power Plant Component Inches Closer to Reality as NTPC’s Site Enabling Works Tender Nears Award

Tarun Karthick
5 Min Read

Campbell Bay | October 26, 2026

The proposed 108 MW gas engine power plant for Great Nicobar Island has moved a step closer to implementation, with NTPC Limited completing the technical evaluation and financial bid-opening stages for a tender covering site enabling works for the project.

According to the NTPC e-procurement portal as of October 26, 2026, the financial bids for the Site Enabling Works Package for Great Nicobar Island Gas Engine Power Project (108 MW) have been opened. The tender status indicates that the process has progressed through technical evaluation and financial bid opening, bringing the preliminary works package closer to the stage of award.

The tender saw five techno-commercial bids opened. The portal lists five bidders as admitted for financial consideration, while one bidder was not admitted because its earnest money deposit (EMD) was found to be invalid. The financial bids were opened on October 20, 2026, and the status was updated on October 21.

The completion of these stages signals progress towards selecting a contractor for the preparatory works required at the proposed power plant site. However, the portal status does not, by itself, confirm that the contract has been awarded.

The comparative price chart uploaded on the portal identifies Surendra Infrastructure Private Limited as the lowest bidder (L1), with a quoted amount of approximately ₹30.78 crore. M/s Nithinsai Construction emerged as the second-lowest bidder, with a quote of approximately ₹31.50 crore. These figures are from the comparative chart, and the identification of the lowest bidder does not mean that NTPC has formally awarded the contract.

The site enabling works package is intended to prepare the proposed project site for the construction of the gas engine power plant. The scope includes clearing and grading the land, earthwork, boundary fencing, drainage and associated civil works.

The preparatory works are an important step towards creating the site infrastructure needed before the main power plant can be constructed. The power plant has a proposed capacity of 108 MW, with a provision of ±5 MW in the tender documents.

While the preliminary works tender has progressed to financial bid evaluation, the separate tender for the main power plant remains open for bidding.

NTPC’s tender for the ‘Great Nicobar Island Gas Engine Power Project 108 MW EPC Package’ has had its bid submission deadline extended for the third time. According to the NTPC e-procurement listing, bids can now be submitted until November 10, 2026, at 1 PM, with bid opening scheduled for 3:30 PM on the same day.

The main EPC package covers the design, engineering, supply, installation, testing and commissioning of the power plant. Its progress will be crucial to moving from site preparation to the actual construction and eventual commissioning of the facility.

The two tenders therefore represent separate stages of the same development: one for preparing the site and another for establishing the power generation facility itself.

The Great Nicobar Project is a major infrastructure initiative planned to transform the southernmost island of the Andaman and Nicobar archipelago into a strategic maritime and economic hub. The project comprises four principal components: an International Container Transshipment Terminal with a proposed capacity of 14.2 million twenty-foot equivalent units (TEUs), intended to strengthen India’s position in regional maritime trade; a Greenfield International Airport designed to handle 4,000 passengers during peak hours; power infrastructure comprising gas- and solar-based power facilities to support the island’s planned infrastructure and development; and a planned township to accommodate the needs associated with the proposed development.

The project is intended to leverage Great Nicobar’s proximity to major east-west international shipping routes while expanding maritime, transport, energy and urban infrastructure.

With the site enabling works tender reaching the financial bid-opening stage, the power plant component appears to be among the first of the project’s four major components to move towards on-ground implementation.